Switchgear Panels Energization and De-Energization Procedure – Electrical Services Commissioning

This document covers the livening up and isolation of electrical supplies from the incoming power supply to the final circuit.

The aim is to have a safe procedure for the livening up electrical supplies during the commissioning period and a safe procedure for isolating electrical supplies where remedial works are required due to defects found during the commissioning period. There are 3 stages for achieving this.

Initial powering up of electrical Power Distribution Centres (PDC’s) with all outgoing circuits isolated and padlocked off. The PDC can now be energized with all outgoing circuits safely isolated. Power Distribution Centres are MDB’s, SMDB’s and MCC’s.

A register of each power distribution centre (PDC) will be created and held by the authorized persons and health and safety department. This will detail the status of each outgoing circuit, if it is locked off and when all test certificates are in place to enable power to be made live giving a central control to safe energization;

Power On/Off requests are the next step and each time an item of plant requires power on, a Power On Request will need to be completed with all the appropriate test certificates, approved Method Statement and pre-commissioning sheets. If Power Off is required then a Power off Request will be completed and when all remedial works are completed the last section of the Power Off Request will be completed and the power supply re-instated.

Access is to be controlled to the following areas for safe energization of LV switch rooms, mechanical plant rooms and distribution rooms. These areas need to be lockable and a permit to work system is required to control access, either permanent or temporary doors are to be fitted which are to be lockable.

Safety notices are to be displayed at the access point to all areas that are live or due to become live. Contact number need to be included and text detailing that these areas are now a permit to access areas.

Responsibilities / Supervision

Communication Requirements

A Pre-construction conference will take place to brief all on this method statement. No one will work during energization and de- energization of the system.

Plant & Equipment Requirements

The minimum Personal Protective Equipment (PPE) on site is:

Energizing Procedure

Power On Request

Fitting of padlocks and completion of the PDC register. Prior to Energization of a PDC the cold testing will have been carried out. At this point the following actions will happen:

Energization of MDB’s

Energization of SMDB’s & Specialist Subcontractor Plant

With all cold tests complete to the SMDB, its feeding cable from the tap off cold tested and a power on request issued, the following will happen

With an electrician at each end of the supply feed confirmation is made that it is safe to energize. At this point power is put on. The register is then updated to include power on.

To provide power to a specialist system item of plant the following actions are required:

Energization of MCC’s & Mechanical Plant

With all cold tests complete to the MCC, its feeding cable from the SMDB tested and a power on request issued, the following will happen:

To provide power to a mechanical item of plant the following actions are required:

Power Off Request

 Reasons for power off

Power off Request Procedure

 The contractor requesting a Power Off is to complete the Power On/ Power Off Request and issue to main contractor.

Test Instruments

Test instruments will be as detailed in each individual system energization method statement. For safety reasons any person working on electrical supplies will use a voltage tester to check that a circuit has been de-energized prior to working on dead electrical circuits.

Calibration

All instruments used will carry current calibration certificates/certificates of conformance to the tolerances specified in the referenced standards.

Safety Aspects & Permit to Work Requirements

Health and Safety procedures will be implemented for this job. The responsible safety officer as per procedure will conduct a routine safety inspection in conjunction with the Safety Rules during testing:

 In order to ensure safe conditions during testing the following rules have to be followed:

Lighting

Safety lights will be used in case of power failure ensuring the good illumination of the working area to aid evacuation if necessary. Adequate lighting shall be provided to ensure the good illumination on the working area.

Emergency Arrangements

Site general safety procedures will be followed. In case of emergency the Safety Officer or the most senior employee present will stop the work, and make the necessary emergency arrangements and report to the assembly points as described during Site Induction Course.

Fire Precautions: There is no significant fire risks associated with this activity but general fire precautionary measures will be taken as per instructions.

Communication from site areas to Site Office via mobile phones issued to all engineers. In emergency situations the users of handheld 2-way radios to be notified if deemed that this can speed up notification of relevant personnel and/or the Site

Risk and Controls

 ITP Electrical Services Commissioning

JSEA / Risk Assessment Electrical Services Commissioning

Supporting Documentation

Other Attachments