Cathodic Protection System Installation Method Statement

Objective of this method statement is to explain the procedure for the Installation of Cathodic Protection System for a construction project in compliance with local and international regulations. This method statement identifies the work related general steps and necessary arrangements, scope of this document includes preparation of equipment, manpower, installation, rebar continuity test for critical… Read More: Cathodic Protection System Installation Method Statement »

Electrical High Voltage Test HV Testing Method Statement

The electrical method statement below provides the brief steps to be carried out during the AC High voltage testing. Method statement applies to the testing of 11 KV switchgear. Testing and commissioning engineer / responsible person shall obtain all necessary clearances and safety document from concern authorities. He shall ensure the work is done as… Read More: Electrical High Voltage Test HV Testing Method Statement »

Electrical Junction Box Installation Method Statement

The purpose of this procedure is to ensure that all works regarding electrical junction box and supports installation for electrical instrumentation works shall be done in accordance with the applicable local standards and all other applicable international codes and standards. Scope of work covers the steps to be followed for the junction box and support… Read More: Electrical Junction Box Installation Method Statement »

MV, LV, ELV & Telecom Cable Pulling and Installation Method for Infrastructure Projects

Prior to commencement of work, all shop drawings will be submitted for approval by consultant/client. Shop drawings will show the layout of pipe and cables as well as the section drawings. Only approved shop drawing will be used for installation. All materials to be used will be submitted for Engineer’s approval in forms of Material… Read More: MV, LV, ELV & Telecom Cable Pulling and Installation Method… »

IP Telephony System Installation Method Statement

All material used at the project site shall be approved prior to the start of IP Telephony system installation works. Materials and documentation relevant to a particular section of works will be checked by the site/project engineer prior to the commencement of work ensuring that these are of the correct type as reviewed by the… Read More: IP Telephony System Installation Method Statement »

Underground Cable Laying Method Statement

Purpose of this method statement is to outline the sequences and methods of works intended to be used for for laying underground 33 kV power and fiber optic cables including the excavation of trench and backfilling. The electrical contractor has the right to adapt the methods of execution as contained in this document from time… Read More: Underground Cable Laying Method Statement »