Category Archives: Electrical Method Statements

You can find helpful method statements for electrical engineering people. Especially for the electrical engineers working in construction industry.

Installation Method Statement for Interior Lighting System Light Fittings & Luminaries

Before start of the installation works exact locations of luminaries will be checked and it should be as per approved RCP (reflected ceiling plan) drawing. Installation shall be carried out by skilled and suitably experienced electricians under supervision of highly competent site supervisors and engineers to ensure the correctness and best quality of installation. Light… Read More: Installation Method Statement for Interior Lighting System Light Fittings &… »

Electrical Installation Method Statement for MDB and MCC

Below is a precise electrical installation method statement that covers installation of main distribution board and MCC panel board in compliance with the approved design, drawings, manufacturer instructions and material submittals. The electrical or MEP project manager is overall responsible for the implementation of this procedure and any relevant documents/standards. Site Engineer will be responsible… Read More: Electrical Installation Method Statement for MDB and MCC »

Cathodic Protection System Installation Method Statement

Objective of this method statement is to explain the procedure for the Installation of Cathodic Protection System for a construction project in compliance with local and international regulations. This method statement identifies the work related general steps and necessary arrangements, scope of this document includes preparation of equipment, manpower, installation, rebar continuity test for critical… Read More: Cathodic Protection System Installation Method Statement »

Electrical High Voltage Test HV Testing Method Statement

The electrical method statement below provides the brief steps to be carried out during the AC High voltage testing. Method statement applies to the testing of 11 KV switchgear. Testing and commissioning engineer / responsible person shall obtain all necessary clearances and safety document from concern authorities. He shall ensure the work is done as… Read More: Electrical High Voltage Test HV Testing Method Statement »

Electrical Junction Box Installation Method Statement

The purpose of this procedure is to ensure that all works regarding electrical junction box and supports installation for electrical instrumentation works shall be done in accordance with the applicable local standards and all other applicable international codes and standards. Scope of work covers the steps to be followed for the junction box and support… Read More: Electrical Junction Box Installation Method Statement »

MV, LV, ELV & Telecom Cable Pulling and Installation Method for Infrastructure Projects

Prior to commencement of work, all shop drawings will be submitted for approval by consultant/client. Shop drawings will show the layout of pipe and cables as well as the section drawings. Only approved shop drawing will be used for installation. All materials to be used will be submitted for Engineer’s approval in forms of Material… Read More: MV, LV, ELV & Telecom Cable Pulling and Installation Method… »